2012 Olympic budget to be significantly higher than originally quoted

The budget for the 2012 London Olympics will be ``significantly higher'' than originally quoted because of increased costs of security, regeneration and contingency plans.

The original budget called for 2.38 billion pounds ($5.12 billion Cdn), but Olympic officials reviewed the cost of the Games after London won the right to host the event in July 2005.

Olympic Delivery Authority acting chairman Roy McNulty said Wednesday he hoped a new budget would be approved by the British government in early 2007, but he wouldn't say what figures the ODA had asked for.

``They are significantly higher,'' McNulty said.

British media reported it could reach more than 5 billion pounds ($10.75 billion Cdn), incorporating a high percentage for contingency plans.

McNulty said venue costs had been ``reasonably accurately estimated,'' but security costs and the budget for the regeneration of the run-down area of London's East End, where the Olympic Park will be built, had both gone up.

The Olympic budget and timetable was put under the spotlight by Jack Lemley, an American engineer who quit as ODA chairman in mid-October. He later said he feared politics would cause projects to be delayed and cost more than expected.

ODA chief executive David Higgins and McNulty both appeared Wednesday before the London Assembly, a 25-member panel which investigates the actions of London Mayor Ken Livingstone and also has an Olympic review role.

``It's a challenging timetable and we will encounter problems, but overall, today, I believe the project is on track,'' McNulty said.

McNulty said work on the Olympic site hadn't been affected by the budget not being finalized.

``The cost is not going to go up on an exponential basis,'' McNulty said. ``If the ODA is given, reasonably soon, the budget we have asked for, including an adequate contingency, I am confident we will deliver the ODA program within that budget.

``I don't expect to have an elastic budget,'' he added.

Higgins said a possible 1 billion pound ($2.15 billion Cdn) bill for a tax on venue construction, which was not included in the original budget, was a ``technicality'' that Chancellor Gordon Brown has said will be solved.

The Assembly listened to a recording of Lemley's interview with The Idaho Statesman newspaper where he spoke of worries to his reputation if he stayed with the ODA.

McNulty said it was a joint decision for Lemley to leave because of a ``mismatch between Jack and our environment here.''

``It's clear and obvious that this project operates in a complex political environment,'' McNulty said. ``Jack clearly found that frustrating.

``People should not confuse the reasons for Jack's departure with concerns he has subsequently expressed in public on his return to the U.S.''

McNulty said London was the first Olympics to be planned with a legacy at the outset.

``Challenge and debate as we move forward do not, in our view, constitute interference,'' McNulty said.

The future use of the Olympic Stadium was also discussed _ with Higgins playing down talk that an English Premier League club, such as West Ham, would use the stadium after 2012.

He said that would only work if a club paid to increase the capacity from the 25,000 seat stadium planned after 2012. But any stadium would have an athletics track, Higgins said.

``The idea of someone giving us 150 million pounds ($323 million Cdn) or more to build an additional 50,000 permanent seats is highly unlikely at this stage and time is certainly running out for those options,'' Higgins said. ``We're not ruling football out. We're very happy to have football, providing it works in a facility which is capable of athletics.''

Higgins said the ODA wasn't in detailed negotiations with any major soccer club.


© The Canadian Press, 2007

Related news
LONDON (AP) _ The overall cost of staging the 2012 London Olympics was set at more than nine billion pounds (C$20.5 billion) Thursday by the British government, three times the ...
The 2012 London Olympics will make a profit despite a 40 per cent increase in the projected overall cost, Mayor Ken Livingstone said Wednesday. Livingstone said costs overruns were ``inevitable.'' ...
A smaller aquatics centre is planned for the 2012 Olympics in an effort to cut spiraling costs. The original project had threatened to double its US$142.5 million budget, so Olympics ...
LONDON (AP) _ The 2012 London Olympics will produce the greatest long-term benefits of any host city since the 1992 Barcelona Games, Mayor Ken Livingstone said Tuesday at the start of a ...
A prominent American sports architectural firm was picked Friday to design the main Olympic stadium for the 2012 Summer Games in London. HOK Sport, which has designed dozens of major ...
GENEVA (AP) _ Britain's hopes of qualifying for the basketball tournament at the 2012 London Olympics are in jeopardy because of a dispute between national authorities and the sport's world governing body. FIBA, the ...

End: 2012 Olympic budget to be significantly higher than originally quoted
Google
Web SportsNews24h.com


Discount Magazine Subscription!

Up to 92% off the cover price!

Search for your favourite magazine now!

© 2006-2007 SportsNews24h.com except where otherwise noted.